Marcos-led council approves P29.98-billion Agus-Pulangi hydro rehab, eyes 25-year PSALM deal with SMC Global, Sta. Clara and a P4/kWh cap
The Economy and Development Council has approved the rehabilitation of Mindanao's seven-plant Agus-Pulangi hydropower complex. The Palace says the work would restore about 1,002 MW and lift yearly output to 4,305 GWh, with the tariff capped at P4 per kWh, subject to ERC approval.

MANILA, Nov. 13, 2026 — The Economy and Development (ED) Council has approved a P29.98-billion project to rehabilitate the Agus-Pulangi Hydropower Complex in Mindanao, the Department of Economy, Planning, and Development (DEPDev) said on Thursday, Nov. 12. The council took up the project at its 12th meeting at Malacañang on Wednesday, Nov. 11, chaired by President Ferdinand R. Marcos Jr.
According to the Presidential Communications Office (PCO), the work would restore the complex’s generating capacity to 1,001.96 megawatts (MW) and raise its yearly output from 3,746 gigawatt-hours (GWh) to 4,305 GWh, an increase of about 15%. The Palace said tariffs would be capped at P4 per kilowatt-hour (kWh), subject to approval by the Energy Regulatory Commission (ERC).
A 25-year partnership, not a sale
The PCO said the project would be carried out through a proposed 25-year public-private partnership (PPP) between the Power Sector Assets and Liabilities Management Corp. (PSALM) and a consortium of San Miguel Global Power Holdings Corp. and Sta. Clara International Corp. The agreement could be extended for another 25 years, subject to performance and government approval.
PSALM has received three unsolicited proposals for the project, two of which remain under evaluation, the PCO said. The government is targeting the selection of the private partner by December 2026, and rehabilitation works are expected to begin in 2027.
During the meeting, Marcos stressed that the National Power Corp. (NPC) must keep its authority and accountability over the plants even as the private partner takes over their day-to-day operation and maintenance, according to the PCO and PTV News. He also called for keeping power rates affordable and competitive so consumers are shielded from possible increases.
PSALM has rejected the idea that the deal amounts to privatization. In September, PSALM president and chief executive Dennis Edward Dela Serna said the state firm wants to use private-sector expertise and resources through the PPP framework, Manila Standard reported. In October, Public-Private Partnership Center Executive Director Rizza Blanco-Latorre told Mindanao Times the project is structured as a concession: the private partner rehabilitates, operates and maintains the plants, while ownership stays with the government and returns fully to it at the end of the concession.
What the rehab covers
The complex has seven plants: Agus I, II, IV, V, VI and VII along the Agus River, which flows from Lake Lanao in Lanao del Sur to Maria Cristina Falls in Iligan City, and Pulangi IV on the Pulangi River in Maramag, Bukidnon, according to Mindanao Times and Manila Standard. Bilyonaryo reported the plants’ capacities as 260 MW for Agus 1 and 2, 213 MW for Agus 4 and 5, 273 MW for Agus 6 and 7, and 255 MW for Pulangi 4. In September, Context.ph reported that the complex was running at roughly 600 MW.
Blanco-Latorre said the scope includes overhauling turbines and generators, repairing dams and waterways, upgrading control, electrical and mechanical systems, civil works, weather forecasting and cascaded hydro operations. The private partner would also handle reservoir improvement, sedimentation management and water-resource programs. Work would proceed one unit at a time, about nine months per unit on average, so the complex keeps supplying power during the rehab, Mindanao Times reported. DEPDev said the project, formally the Agus-Pulangi Hydroelectric Power Plants Rehabilitation and Asset Management Project, is also meant to address aging facilities and environmental concerns, BusinessWorld and BusinessMirror reported.
“Reliable and affordable energy is essential for Mindanao to realize its growth potential,” Economy Secretary and ED Council Vice-Chair Arsenio M. Balisacan said in the DEPDev statement, as quoted by BusinessWorld.
Two price tags
The P29.98 billion is the cost DEPDev gave for the approved project. In October, Mindanao Times reported that the proposal to rehabilitate and operate the complex was worth P69.72 billion, a figure it gave while reporting on the PPP Center’s briefing. None of the sources explains the gap between the two figures.
What happens next
ED Council approval is not the final step. Under the PPP Code, an unsolicited proposal goes through a comparative challenge in which other firms may submit competing offers. Blanco-Latorre told Mindanao Times the challenge period can run from 90 days to one year, and the original proponent has 30 days to match any better offer. The award, notice and contract signing follow on short deadlines after that.
The PCO is targeting December 2026 for the partner selection. In September, however, PSALM said it expected to hold the challenge and award the project in 2027, Manila Standard and Bilyonaryo reported. The P4-per-kWh cap still needs the ERC’s approval. Officials told Mindanao Times in October that service fees are expected to rise after the overhaul because of the private capital involved, and that any rate adjustment would go through the ERC, including stakeholder participation and public hearings.
Sources
This story was compiled and rewritten from reporting by 10 outlets.
- 1Philippine News Agency“PBBM steps up push for key energy, flood control, social protection projects,” by Ruth Abbey Gita-Carlos, Nov. 12, 2026www.pna.gov.ph ↗
- 2BusinessWorld“Agus-Pulangi hydro rehabilitation wins ED Council approval,” by Justine Irish D. Tabile, Nov. 12, 2026bworldonline.com ↗
- 3BusinessMirror“Economic council approves P56.8B in projects,” by Bless Aubrey Ogerio, Nov. 13, 2026businessmirror.com.ph ↗
- 4BusinessWorld“Palace advances Agus-Pulangi rehab, flood pumps and bridge projects,” by Erika Mae P. Sinaking, Nov. 11, 2026bworldonline.com ↗
- 5PTV News“PBBM champions inclusive infrastructure dev't in 12th EDC Meeting,” by Dean Aubrey Caratiquet, Nov. 12, 2026ptvnews.ph ↗
- 6RMN“PBBM, isinusulong ang rehabilitasyon ng Agus-Pulangi power plants sa Mindanao,” by RadyoMaN Manila, Nov. 12, 2026rmn.ph ↗
- 7Mindanao Times“P69.7-B Agus-Pulangi hydro rehab, joint venture with PSALM up for government review,” by Nova Mae Francas, Oct. 29, 2026www.mindanaotimes.com.ph ↗
- 8Manila Standard“PSALM: Agus-Pulangi PPP deal does not involve privatization,” by Alena Mae S. Flores, Sept. 18, 2026manilastandard.net ↗
- 9Bilyonaryo“Ramon Ang-led San Miguel bags original proponent status for Mindanao's Agus-Pulangi hydropower rehab,” by Bilyonaryo staff, Sept. 3, 2026bilyonaryo.com ↗
- 10Context.ph“SMC-led consortium secures original proponent status for Agus-Pulangi Hydro rehab unsolicited bid,” Sept. 3, 2026context.ph ↗